CTM 9.6 Chemical Tanker Manual
CTM
Cargo Discharging Operations
Doc No.: CTM 9.6
Revision: 01
Date: 15 Oct 2024
Issued by: DPA
Approved by: MD

1. APPLICATION

This document applies to all Chemical Tankers managed by the Company.

2. PURPOSE

The purpose of this document is to provide guidelines and instructions for the safe and efficient discharging of cargo from chemical tankers.

3. CARGO HANDLING PLAN

3.1 Basic Information

The Chief Officer shall prepare a Cargo operation plan that provides a detailed sequence of cargo and ballast operations. It shall cover the following:

Additionally, as required or applicable:

Note:

3.2 Discharging methods

The Cargo Operation plan shall clearly specify:

3.3 Involvement of Engine Department

The Chief Officer shall discuss relevant items of the Cargo Operation plan with the Engine Department, which shall include the following:

Note:

4. REFERENCES

Follow precautions as detailed in the following Industry guides:

5. ULLAGING PRIOR TO DISCHARGE (CDI 5.1.6)

Before commencing discharge of cargo and in conjunction with the surveyor/receiver’s representative:

Note:

If discrepancy exceeds 0.5%:

In taking ullages and temperatures, Chief Officer shall consider the following points:

Note:

6. PRIOR TO DISCHARGE (CDI 5.1.6)

6.1 Information to be exchanged with terminal before unloading operation

The Chief Officer shall ensure the following information is exchanged:

6.2 Preparation prior to discharge

Prior to discharge, the Chief Officer shall ensure:

7. PUMPING SYSTEMS

7.1 Speed of discharge

Note:

7.2 Cargo pumps

Chief Officer shall ensure that the flow to the pump suction does not fall below the pumping rate.

Note:

7.3 Submerged centrifugal pumps


Note:

7.3.1 Control and operation of centrifugal pumps

During operation, Chief Officer/OOW shall give due consideration to:

Information:

7.3.2 Discharge valves

Chief Officer shall ensure proper control of the discharge valves. Information:

7.3.3 Cavitation

Chief Officer/OOW shall avoid cavitation as far as possible. Information:

7.3.4 Discharging using more than one pump

When cargo is being discharged from more than one tank simultaneously through the common line or jumping hose:

7.4 Positive displacement pumps

7.4.1 General

This type of pump includes:

7.4.2 Reciprocating pumps

Chief Officer/OOW shall take precautions to avoid racing, if necessary by slowing the pump.

Coution:

7.4.3 Screw pumps

Information:

Chief Officer/OOW shall ensure:

7.4.4 Operation

Chief Officer/OOW shall ensure:

8. CARGO DISCHARGING

8.1 General

When deep well cargo pumps are used in parallel to discharge a group of tanks into a common discharge line, Chief Officer/OOW shall ensure:

8.2 Commencing a transfer using deep well pumps

Note:

The following procedure is common to all types of deep well pumps. Chief Officer and OOW shall follow the steps below when commencing discharge:

Note:

  1. The number of full tanks (98% capacity) to be commenced as a group must not exceed.
  2. Note:

    • In case of bulk discharging with deep well pumps, all tanks should be dropped to below 95 percent alarm level, one by one.
      In case ship needs to start more than one tank, this should be carefully evaluated and a risk assessment done. Approval from Master must be taken.
  3. Ensure that cargo tanks, which are not part of the group to be initially discharged, are isolated from the group.
  4. Start the pumps in pairs at a minimum 100 bar hydraulic pressure and open the pump discharge valves. At that pressure, the pump will run smoothly but produce minimal cargo backpressure.
  5. Monitor the ullage levels in all tanks in the group while starting the pumps.
  6. When all pumps are running at 100 bar hydraulic pressure, check:
    • Ullage levels in all tanks in the group and
    • The cargo back pressure at the pump gauges and/or the manifold.
  7. When satisfied that the situation is stable, increase the hydraulic pressure to each pair of pumps in turn in increments of 10-20 bar until:
    • All pumps in the group are running at the same hydraulic pressure and
    • The required cargo back pressure at the manifold has been achieved.
  8. Reduce the level of all cargo tanks with the same cargo to below 90% prior to increasing the discharge rate to the agreed maximum rate.
  9. To add additional pumps to the group at a later stage in the discharge operation, reduce the hydraulic pressure of the pumps already running to the level specified in step IV above. Open the isolator valves of the additional pumps and start them at the same pressure, then open their discharge valves.
  10. Tanks are to be discharged as quickly as possible to achieve backpressure as agreed between vessel and shore.

8.3 Final Stages of Discharging - Trim and List of Vessel

At the final stage of discharging (stripping and/or squeezing (sweeping) the cargo), achieve correct trim and list to obtain maximum out-turn in minimum time. This shall be achieved by:


Coution:


Note:

9. TANK INSPECTION

Information:

Note:

Chief Officer shall:


Note:

10. OUTTURN

Chief Officer/ Master shall ensure:

11. CARGO RESIDUE

Chief Officer shall ensure:

Note:

12. SWEEPING (SQUEEGING) OF CARGO TANKS


Coution:


Coution:


Master/Chief Officer shall ensure the following prior to/during entry into any tank:

In case shore contractors are used:

13. PORTABLE CARGO PUMP

Storage on Board Forecastle / Bosun store

The portable pump and flexible hoses must be cleaned and ready for a new pumping job before the equipment is placed in the storage room onboard.

The storage room must be clean and dry, and the pumping equipment must have easy accessibility.

The hydraulically driven portable cargo pump:


Note:


Officers shall familiarize themselves with the use of the portable cargo pump by referring to the maker’s manuals. A quarterly drill on the actual rigging and operation of the portable cargo pump should be carried out as per Drill schedule HSSEQ-03. During the drill, the portable pump should be rigged and tried out as it will be done in an emergency scenario.

The portable pump must be tested regularly as per the PMS. Prior to rigging the portable pump, the vessel should carry out a risk assessment and send it to the respective MSI for review.

14. EMERGENCY SHUTDOWN PROCEDURE


Note:


15. BUTTERFLY AND NON-RETURN (CHECK) VALVES

16. VALVE OPERATION

Chief Officer and OOW shall:

17. REFERENCED FORMS AND CHECKLISTS