OTM-7.10 Oil Tanker Manual
OTM
Maintenance and Inspection
Doc No.: OTM 7.10
Revision: 01
Date: 15 Oct 2024
Issued by: DPA
Approved by: MD

1. INERT GAS - MAINTENANCE AND INSPECTION

The safety arrangements are an integral part of the inert gas system and it is essential for the ship's staff to give special attention to them during any inspection. All maintenance and inspections contained in this matter shall be recorded in the Inert Gas Record Book, OTM 7.11 I.G & IGG Monthly Maintenance Checklist or in the PMS System.

Tables below outline the maintenance programme:

Component Preventive Maintenance Maintenance Interval
Flue Gas Isolating Valves Operate the valve Once a week and Before start-up
Lubricate valve Before start-up
Cleaning with compressed air or valve steam Before operating
Dismantling for inspection and cleaning Boiler shutdown
Flue Gas Scrubber S.W. Water Flush and FW wash After Use
Cleaning of demister regulators and temp probes for inspection Three months
Internal inspection through inspection doors Six months
Opening for full inspection Dry docking
Overboard Pipes and Valve from Flue Gas Scrubber Flushing with scrubber water pump for about 1 hour After use
Dismantling of the valve for overhaul / inspection of pipeline and overboard stub pipe Dry docking
Blowers Vibration checks While running
Flushing After Use
Internal inspection through hatches After flushing and six months
Dismantling for full overhaul of bearing shaft tightening and other necessary work Dry docking
Deck Mechanical Non-return Valve Moving and lubricating the valve One week and before start
Opening for internal inspection One year
Pressure Vacuum Valves and High Velocity Valves Operating and lubricating the valves Six months
Opening for full overhaul and inspection One year
Deck Isolating Valves Opening for overhaul One year
Emergency Isolation valve for Inert Gas system to ballast tanks Operating and lubricating the valves Six months
Gas Pressure Regulating System Removal of condensation in instrument air supply Before start
Opening of gas pressure regulating valves for overhaul Dry dock
Liquid-filled pressure vacuum breaker Check liquid level when system is at atmospheric pressure When opportunity permits and every six months
Deck seal Dismantling of level regulators / float valves for inspection Six months
Opening for total internal inspection One year
Overhaul of automatic valves One year

Table 1: IGS maintenance recommendations

Equipment Maintenance Action Frequency
UP-TAKE VALVES Spindle of valve should be greased Every voyage
SCRUBBER Scrubber should be opened, and interior and nozzles cleaned in order to prevent blockage Every 6 months
DEMISTER At the same time clean the PAD with fresh water Every 6 months
FAN Clean the IMPELLER and CASING with fresh water and inspect the drain line against sticking and clogging Every time after water use
FAN MOTOR Insulation test to be carried out (before operation) Every voyage
OXYGEN ANALYSER O2 analyser should be adjusted to "O" zero by N2 gas span Before supplying inert gas
RECORDERS Check operations of O2 analyser and pressure Before supplying inert gas
SUPPLY OF AIR Check air pressures of individual installation (before operation) Every operation/voyage (before)
SUPPLY OF AIR Reducing valves should be inspected, cleaned, and overhauled (before operation) Every operation/voyage (before)
BREATHER VALVES As far as possible, the breather valves should be inspected, overhauled, and cleaned as necessary Every 3 months

The inspection carried out shall be recorded in OTM 7.11 -- I.G & IGG Monthly Maintenance Checklist and submit to the office when ever asked.

2 CARGO PIPELINES AND HOSES

3 HYDROSTATIC TESTING OF CARGO PIPING

Testing of the cargo pipes should be preferably carried out using water in connection with a tank cleaning operation.

  1. The basic steps of the procedure are the following:
  2. A more detailed procedure is outlined below:

Note: