| OTM-7.12 |
Oil Tanker Manual OTM Inert Gas System |
Doc No.: OTM 7.12
Revision: 01 Date: 15 Oct 2024 Issued by: DPA Approved by: MD |
1. APPLICATION
This document applies to Officers onboard fully managed Tank vessels.
2. PURPOSE
The purpose of this document is to specify requirements for safe operation of Inert Gas Systems on product and crude oil tankers.
3. REQUIREMENTS
Follow ISGOTT 6th Edition chapter 7.1 (fixed inert gas system).
All oil and Chemical tankers should comply with the following guidance for carriage of cargo in inerted condition.
| Ship product | Above 20,000 DWT keel laid after July 1986 but before 1st January 2016 | Tanker above 8,000 DWT keel laid after 1st January 2016 | ||
|---|---|---|---|---|
| Cargo tanks < 3,000 m³ | Cargo tanks > 3,000 m³ | |||
| Crude oil | IG Required | IG Required | IG Required | |
| Petroleum products Flashpoint < 60°C | IG Required | IG Required | IG Required | |
| Chemicals Flashpoint < 60°C | IG Not Required (1) | IG Required (2) | IG Required (2,3) | |
| Other Liquid Substances Flashpoint < 60°C | IG Not Required (1) | IG Required | IG Required (2,3) | |
1. Subject to each tank washing machine nozzle not exceeding 17.5m³/hr and total capacity of the tank cleaning machines is less than 110m³/hr.
2. For chemical tankers, the application of inert gas may take place after the cargo tank has been loaded, but before commencement of unloading and shall continue to be applied until that cargo tank has been purged of all flammable vapours before gas-freeing. Only nitrogen is acceptable as inert gas under this provision.
3. For tankers of 8,000 tonnes deadweight and upwards but less than 20,000 tonnes deadweight constructed on or after 01 January 2016, in lieu of fixed installations as required by paragraph 5.5.4.1 of SOLAS II-2, Regulation 4, the Administration may accept other equivalent arrangements or means of protection in accordance with SOLAS Regulation I/5 and paragraph 5.5.4.3 of SOLAS II-2, Regulation 4.
Note:
- For vessels with operational Nitrogen plant carrying chemicals with flashpoint below 60C, cargo tank should be inerted. This may be done after loading but tank should be inerted prior discharging and discharging done under inert condition. In case of any deviation from these guidelines, company office should be informed and consulted.
Note:
- For vessels with operational Nitrogen plant carrying chemicals with flashpoint below 60C, cargo tank should be inerted. This may be done after loading but tank should be inerted prior discharging and discharging done under inert condition. In case of any deviation from these guidelines, company office should be informed and consulted.
In the context of this matrix, the terms:
- "Petroleum products" may be referred to as MARPOL Annex I products.
- "Chemicals" are products listed in chapter 17 and 18 of the IBC Code.
- "Other Liquid Substances" are those products that are listed in IBC chapter 18 and evaluated to fall outside MARPOL Categories X, Y or Z. These products are listed as other substances, "OS".
4. RESPONSIBILITIES
- Chief Engineer - Prepare IG plant prior to use
- Chief Officer - Coordinate with the chief engineer to prepare the IG plant. Give sufficient notice to the engine room for IG plant.
- Deck Officers - Assist chief officer as required to monitor IG parameters.
- Engine Officers - Assist chief engineer as required to monitor IG parameters.
5. OPERATION OF INERT GAS SYSTEM
Cargo tanks must be kept inerted and under positive pressure at all times, except when required for man entry.
- Inert cargo tanks prior to loading.
- Keep oxygen content in cargo tanks below 8% at all times.
- Do not allow tank pressure to fall below 100 mmWG at any time.
- Purge cargo tanks to HC 2% prior to gas freeing.
Warning:
- Refer to ISGOTT Flammability diagram (Figure 1.1) for Purging & Gas Freeing.
Use the Inert Gas system for:
- Inerting cargo tanks
- During discharging
- Crude oil washing
- Top up pressure during voyage
- De-ballasting of cargo tanks
- Purging before gas freeing
(By Gas freeing from a “Purged condition (HC=2% VOL)” to the “Gas free condition (HC=<1% LEL)”and until steady 21% by volume oxygen reading is sufficient dilution of such toxic gases to below their OEL-TWA limits will have been achieved.)
Coution:
- Oxygen content of the Inert Gas delivered to deck should always be <5%.
Note:
- 1. Use TNK 09 -Inert Gas Operation Log for record keeping
- 2. Use E83 – IGG Alarms prior Discharge Operation
Startup procedure
Note:
- Use Form E4A for several test.
- Ensure the following calibrated as per maker’s instructions & working:
- Portable oxygen analyzer at least 24 hours prior to arrival
- Fixed oxygen analyzer at least 24 hours prior to arrival
- Inert gas pressure indicator and recorder
- Oxygen and pressure recorders
- Display maker’s instructions near the oxygen analyzer unit
- Train engineers as required
- Mark date and type of operation on the recorder prior using the inert gas plant.
- Ensure the following:
- The boiler or inert gas generator is producing inert gas with oxygen content no more than 5% by volume
- Power is available for all control, alarm, and automatic shutdown operations
- Scrubber & deck seal pump operation to maintain correct water level.
- Test operation of the alarm and shutdown features of the system for scrubber water supply, and high and low levels
- Check that the fresh air inlet valve is closed and the blank secured
- Shut off the air to any air sealing arrangements for the flue gas isolating valve
- Open the flue gas isolating valve
- Open the selected blower suction valve. Ensure that the other blower suction and discharge valves are shut unless it is intended to use both blowers simultaneously
- Start the blower
- Test blower "failure" alarm
- Open the blower discharge valve
- Open the re-circulating valve to enable the plant to stabilise
- Open the inert gas regulating valve
- Check that the oxygen content of the inert gas is 5% by volume or less
- The inert gas system is now ready to deliver gas to the cargo tanks
- Ensure individual tank I.G. valves are open and tank valves not in use are closed and locked
Note:
Shutdown Procedures
- Close deck isolating valve once:
- Oxygen content in cargo tanks is no more than 8% by volume
- Required pressure achieved in cargo tanks
- Shut the gas pressure regulating valve
- Shut down the inert gas blower
- Close the blower suction and discharge valves.
- Check that the drains are clear. Run the water washing system for at least 10 minutes on the blower while it is still rotating with the power supply off.
- Close the flue gas isolating valve and open the air sealing system
- Keep the water supply to the scrubbing tower on for one (1) hour
- Fresh water wash the scrubber
- Maintain water level in deck seal with low level alarm in operation.
- Do not switch off deck seal pump.
- Keep power to the control panel switched on at all times, unless the vessel is gas free
Coution:
Safety Checks When the IG Plant is Shutdown
- Daily check deck seal water supply and level.
- In cold climate ensure the following to prevent ice formation:
- Anti-freeze system for deck seal & PV breaker in order
- Keep IG system free of icing
- Check all moving parts
- Switch on heating for P/V valves, if fitted or lift manually to free them
- Avoid lifting PV Valve during cargo operation as far as possible
- Agree manual lifting frequency
- Agree manual operation of PV valves in ship/shore safety checklist.
- Check positive water flow in deck seal
- Protect essential valves on the IG system with suitable grease and canvas cover
- Flame arrestors free of snow or ice
- Record IG pressure in deck log book at least once per watch
- Do not allow pressure in cargo tanks to drop below 100 mmWG
Coution:
Possible Failures and Action to be Taken
- Cause of high oxygen content:
- Poor combustion control at the boiler, especially under low load conditions
- Drawing air down the uptake when the boiler gas output is less than the I.G. blower demands, especially under low load conditions
- Air leaks between the inert gas blower and the boiler uptake
- Faulty operation or calibration of the oxygen analyzer
- Operation in re-circulation mode. Entry of air into the inert gas main through the pressure vacuum valves or mast risers due to incorrect operation
- Suspend cargo operation, water washing & crude oil washing in case of IG failure.
- Reason for low pressure during cargo discharging or de-ballasting operation:
- Accidental closure of the inert gas valves.
- Faulty operation of the automatic pressure control system
- Inadequate blower pressure, or cargo rate more than blower output
- Reduce rate to maintain positive pressure.
- Suspend operation if positive pressure cannot be maintained.
Coution:
Note:
Coution:
6 CARRIAGE OF CARGOES UNDER INERTED CONDITION
Set and lock individual tank IG isolation valves as required (open or close)
Note:
- The key should be in chief officer’s custody.
Loading Operations
- Check flame screens of mast riser, PV Valves and replace if necessary
- Keep deck isolation valve closed
- Close all openings to cargo tanks except agreed venting arrangement
- Suspend cargo operation in case of bad weather as agreed in ship/shore safety checklist
Note:
- Always maintain positive pressure in cargo tanks.
Discharging Operations
Coution:
- Discharging without IGS needs company office approval.
- Give sufficient notice to engine room for IG
- Vent IG to atmosphere until oxygen content < 5%
Coution:
- Suspend cargo operation in case of IG Failure
- Verify oxygen content at top and middle level in cargo tanks prior to crude oil washing.
Note:
- For Products having flash point >60C (Refer ISGOTT Chapter 11, Section 11.1.9.2).
7.INERT GAS EMERGENCY PROCEDURES
- Consider IG Failure if:
- Quantity & Quality of IG is not delivered
- Positive Pressure in cargo tanks cannot be maintained.
- Shut down of IG Plant.
- Immediate actions to prevent air in the tanks:
- Suspend discharging / tank washing / de-ballasting operations.
- Cease ullaging and sampling.
- Close deck isolation valve and open the vent valve between isolation valve and gas regulating valve
Note:
- Resume discharging only when IG Plant is restored & tanks inerted.
- Please refer to ISGOTT 11.1.11 for precautions during Inert gas system failure.
- Avoid following during re-inerting (If required):
- Ullaging
- Dipping
- Sampling
- Introduction of any other equipment
- If oxygen content in the tanks falls below or rises above 8% take precautions against:
- Static electricity - Refer ISGOTT 6th Edition Chapter 3
- Pyrophoric ignition - Refer ISGOTT 6th Edition Chapter 1.5.3
Additional Follow-up Action on Crude Oil Tankers
Note:
- Always maintain positive pressure in cargo tanks.
Coution:
- Discharging without IGS needs company office approval.
Coution:
- Suspend cargo operation in case of IG Failure
Note:
- For Products having flash point >60C (Refer ISGOTT Chapter 11, Section 11.1.9.2).
- Quantity & Quality of IG is not delivered
- Positive Pressure in cargo tanks cannot be maintained.
- Shut down of IG Plant.
- Suspend discharging / tank washing / de-ballasting operations.
- Cease ullaging and sampling.
- Close deck isolation valve and open the vent valve between isolation valve and gas regulating valve
Note:
- Resume discharging only when IG Plant is restored & tanks inerted.
- Please refer to ISGOTT 11.1.11 for precautions during Inert gas system failure.
- Ullaging
- Dipping
- Sampling
- Introduction of any other equipment
- Static electricity - Refer ISGOTT 6th Edition Chapter 3
- Pyrophoric ignition - Refer ISGOTT 6th Edition Chapter 1.5.3
Pyrophoric iron sulphide deposits (pyrophors), formed when hydrogen sulphide gas reacts with rusted surfaces in the absence of oxygen, may be present in the cargo tanks of crude oil tankers. These deposits can heat to incandescence when coming into contact with air. The failed inert gas system must be repaired and restarted, or an alternative source of inert gas provided, before discharge from inerted tanks is resumed.
Additional Follow-up Action on Product Tankers
Tank coatings usually inhibit the formation of pyrophors in the cargo tanks of product tankers. If it is considered totally impracticable to repair the inert gas system, discharge may therefore be resumed with the written agreement of all interested parties, provided that an external source of inert gas is provided or detailed procedures are established to ensure the safety of operations.
- The following precautions should be taken:
- Devices to prevent the passage of flame or flame screens (as appropriate) are in place and are checked to ensure that they are in a satisfactory condition.
- Valves on the vent mast risers are opened.
- No free fall of water or slops is permitted.
- No dipping, ullaging, sampling or other equipment is introduced into the tank unless essential for the safety of the operation. If it is necessary for such equipment to be introduced into the tank, it should be done after at least 30 minutes have elapsed since the injection of inert gas has ceased.
- All metal components of any equipment to be introduced into the tank should be securely earthed. This restriction should be applied until a period of five hours has elapsed since the injection of inert gas has ceased.
Coution:
- Any failure of the IG system shall be reported to the office and the charterers in accordance with the Charter Party.
8.REFERENCED FORMS AND CHECKLISTS
- TNK 09 - Inert gas operation log
- E04A - Inert gas system log (Engine dept)
9.APPENDICES
- OTM 7.10 Maintenance and inspection
- OTM 7.11 I.G & IGG monthly maintenance checklist